Overall condition: Poor
Superstructure condition rating: Poor(4 out of 9)
Substructure condition rating: Poor(4 out of 9)
Deck condition rating: Good(7 out of 9)
Sufficiency rating: 17.8 (out of 100) View more at BridgeReports.com
Categories
Update Log
September 23, 2021: Updated by Nathan Holth: Slated for demolition and replacement. Added estimated demolition dates.
September 23, 2021: Updated by Jason Smith: Scheduled to be replaced; bridge available for adoption and relocation.
July 27, 2013: Updated by Dave King: Fixed location per to do list
October 9, 2012: New photos from J.R. Manning
September 20, 2010: New Street View added by Nathan Holth
This and two other bridges along WI Hwy. 130/133 are being given away. Deadline to obtain the packages by WIDOT is October 31st. Details here: https://bridgehunterschronicles.wordpress.com/2021/09/23/thr...