contract awarded Jan., 19, 1875 to Joseph Preston (superstructure probably subcontracted to Corwin/Lambertville Iron Works per HAER), superstructure replaced around 1895.
Builders
- Cowin Iron Works of Lambertville, New Jersey (probable subcontractors for superstructure per HAER)
- Joseph G. Preston (prime contractor & substructure)
- Lambertville Iron Works of Lambertville, New Jersey (probable subcontractors for superstructure per HAER)
Design
Assuming HAER is correct re: Corwin/Lambertville, the bridge would have been a vertical endpost, cast iron compression member, Pratt pony truss.
Approximate latitude, longitude
+40.23848, -74.83106(decimal degrees) 40°14'19" N, 74°49'52" W (degrees°minutes'seconds")