As per an article printed in the Reading Eagle sealed proposals will be received by North Heidelberg Township,Berks County,Pa.via the online PennBid Program until 11:00am on Monday August 21st,2017,for the following:Klopp Road Bridge replacement.This work will consist of the removal and replacement of a 6-foot span metal and concrete bridge with a new 7.5 foot diameter metal structural plate pipe culvert with concrete or metal head/endwalls,replacement of about 60 feet of guiderail,and streambank improvements to improve stream and road conditions.I didn't know they were replacing this bridge with a culvert.
You might be right,Dana and Kay.They didn't give a location,like which roads it is between.I don't see another bridge on that road so it might be safe to assume that is the one.When i get further information via the newspaper i'll pass it on.
George this MAY be bridge in question, didn't see in NBI Data Base
As per an article printed in the Reading Eagle on 11/4/17 the pre-cast for the head and end walls will now be completed by McCarthy Engineering of Wyomissing Pa,not Reamstown Excavating of Denver Pa,which is doing the project.It was decided to make the switch after Reamstown Excavating said that it would take six to eight weeks for the fabrication of the walls,while McCarthy said that it could be done in two to three weeks.The work will cost between
$1000 and $1,500.The cost of the work will be deducted from what the board is going to pay Reamstown Excavating for the overall project,which was $71,163.